EVM Performance

Program Manager
CreateEditApproveAccept residualRun simulationsEdit EVMCloseExportAudit

Earned Value Performance

Cost and schedule performance across control accounts, with integrated variance and forecast-at-completion analysis.

Cost Perf. Index (CPI)

0.939

Cost overrun

Schedule Perf. Index (SPI)

0.922

Behind schedule

Cost Variance (CV)

-$4.3M

-6.5% of EV

Est. at Completion (EAC)

$139.8M

VAC -$8.5M

Significant Variance — Action RequiredBAC $131.3M · TCPI(EAC) 0.939

Cost and/or schedule performance is materially below plan. Escalate recovery planning and reassess the estimate at completion.

Cumulative Performance Curves

PV / EV / AC over time
Planned Value (PV)Earned Value (EV)Actual Cost (AC)

Control Account Performance

Period 2026-05 · click a row to expand variance detail

Control AccountBACEVACCPISPIEACVAC
CA-1200
Transformer & Switchgear
$42M$21.6M$23.8M0.910.90$46.3M-$4.3M
CA-2100
Foundations & Structures
$58M$28.2M$30.5M0.930.91$62.7M-$4.7M
CA-3400
SCADA Integration
$18.5M$10M$9.3M1.071.01$17.3M$1.2M
CA-1500
Site Civil & Safety
$12.8M$6.6M$7.1M0.940.92$13.7M-$872.7K

Program rollup across 4 control accounts · 131,300,000 total budget at completion.