Back to register
R-003
SCADA integration interface incompatibility
ActiveControl Center SCADA·Technical·Owner: L. Nguyen
Pre-MitigationHigh
$382.5K
Expected monetary value
Score 9.0
45% likely
ResidualModerate
$84K
Expected monetary value
Score 8.3
20% likely
Mitigation Effect
$298.5K
EMV reduction from response plan
Mitigation cost $210K70% effective
Cause (because of)
Legacy protocol not fully documented
Uncertain Event (there is a risk that)
New SCADA platform fails to interface with field RTUs
Consequence (which would lead to)
Rework of integration layer and delayed cutover
Root Cause
Legacy protocol not fully documented
Trigger / Threshold
Factory acceptance test reveals protocol mismatch
Early Warning Indicator
Factory acceptance test reveals protocol mismatch
Assumptions
Baseline assumptions per approved project execution plan.