R-007
Specialized commissioning labor shortage
ActiveSubstation Upgrade·Resource·Owner: K. Larsson
Pre-MitigationModerate
$350K
Expected monetary value
Score 6.8
50% likely
ResidualModerate
$106.4K
Expected monetary value
Score 6.0
28% likely
Mitigation Effect
$243.6K
EMV reduction from response plan
Mitigation cost $130K65% effective
Cause (because of)
Regional competition for protection & control technicians
Uncertain Event (there is a risk that)
Insufficient qualified staff during commissioning peak
Consequence (which would lead to)
Commissioning slips and overtime premium costs
Root Cause
Regional competition for protection & control technicians
Trigger / Threshold
Staffing plan falls below 80% at T-minus 90 days
Early Warning Indicator
Staffing plan falls below 80% at T-minus 90 days
Assumptions
Baseline assumptions per approved project execution plan.