Risk Register

Program Manager
CreateEditApproveAccept residualRun simulationsEdit EVMCloseExportAudit
Back to register
R-007

Specialized commissioning labor shortage

ActiveSubstation UpgradeResourceOwner: K. Larsson
Pre-MitigationModerate

$350K

Expected monetary value

Score 6.8

50% likely

ResidualModerate

$106.4K

Expected monetary value

Score 6.0

28% likely

Mitigation Effect

$243.6K

EMV reduction from response plan

Mitigation cost $130K65% effective

Cause (because of)

Regional competition for protection & control technicians

Uncertain Event (there is a risk that)

Insufficient qualified staff during commissioning peak

Consequence (which would lead to)

Commissioning slips and overtime premium costs

Root Cause

Regional competition for protection & control technicians

Trigger / Threshold

Staffing plan falls below 80% at T-minus 90 days

Early Warning Indicator

Staffing plan falls below 80% at T-minus 90 days

Assumptions

Baseline assumptions per approved project execution plan.