NERC CIP compliance documentation gap
ActiveControl Center SCADA·Regulatory·Owner: A. Volkov
Pre-MitigationModerate
$360K
Expected monetary value
Score 7.5
40% likely
ResidualLow
$68.4K
Expected monetary value
Score 5.3
18% likely
Mitigation Effect
$291.6K
EMV reduction from response plan
Mitigation cost $110K70% effective
Cause (because of)
Evolving compliance standards and audit scope
Uncertain Event (there is a risk that)
Audit finds documentation deficiencies
Consequence (which would lead to)
Penalties and remediation effort
Root Cause
Evolving compliance standards and audit scope
Trigger / Threshold
Regulator schedules compliance audit
Early Warning Indicator
Regulator schedules compliance audit
Assumptions
Baseline assumptions per approved project execution plan.