Risk Register

Program Manager
CreateEditApproveAccept residualRun simulationsEdit EVMCloseExportAudit
Back to register
R-014

Right-of-way easement acquisition delay

ActiveTransmission Line 230kVLand/ROWOwner: S. Patel
Pre-MitigationHigh

$720K

Expected monetary value

Score 10.0

60% likely

ResidualModerate

$285K

Expected monetary value

Score 6.8

38% likely

Mitigation Effect

$435K

EMV reduction from response plan

Mitigation cost $150K55% effective

Cause (because of)

Multiple private landowners and negotiation complexity

Uncertain Event (there is a risk that)

Easements not secured before construction start

Consequence (which would lead to)

Construction sequencing delay and legal cost

Root Cause

Multiple private landowners and negotiation complexity

Trigger / Threshold

Landowner rejects appraisal offer

Early Warning Indicator

Landowner rejects appraisal offer

Assumptions

Baseline assumptions per approved project execution plan.