Right-of-way easement acquisition delay
ActiveTransmission Line 230kV·Land/ROW·Owner: S. Patel
Pre-MitigationHigh
$720K
Expected monetary value
Score 10.0
60% likely
ResidualModerate
$285K
Expected monetary value
Score 6.8
38% likely
Mitigation Effect
$435K
EMV reduction from response plan
Mitigation cost $150K55% effective
Cause (because of)
Multiple private landowners and negotiation complexity
Uncertain Event (there is a risk that)
Easements not secured before construction start
Consequence (which would lead to)
Construction sequencing delay and legal cost
Root Cause
Multiple private landowners and negotiation complexity
Trigger / Threshold
Landowner rejects appraisal offer
Early Warning Indicator
Landowner rejects appraisal offer
Assumptions
Baseline assumptions per approved project execution plan.